cooling door

Alexander Harrowell a.harrowell at gmail.com
Sun Mar 30 19:29:47 UTC 2008


On Sun, Mar 30, 2008 at 8:16 PM, Buhrmaster, Gary <gtb at slac.stanford.edu>
wrote:

>
>
> > 10-20mW (or more) of nuclear power/gensets.
>
> While I would be much amused to see the response
> in the area when Paul requested approval to site a
> nuclear reactor on the Peninsula, I do not think
> even Paul is quite up to that challenge


Not so long up-thread, people were opposing water cooling on the grounds it
was too dangerous...what if something leaked? Now we're talking sticking a
nuclear reactor in your data centre.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.nanog.org/pipermail/nanog/attachments/20080330/db93fbbc/attachment.html>