Level 3, again

virendra rode // virendra.rode at gmail.com
Tue Feb 12 22:05:49 UTC 2008


-----BEGIN PGP SIGNED MESSAGE-----
Hash: SHA1

fyi -/


- -------- Original Message --------
Subject: [Outages] FW: Level(3) Service Affecting Maintenance -
GCR#180226 -	Scheduled
Date: Tue, 12 Feb 2008 13:22:18 -0700
From: Raman Sud <ramans at cwie.net>
To: outages at isotf.org <outages at isotf.org>


Level (3) Communications - Network Change Control (NCC)
***SCHEDULED MAINTENANCE ADVISEMENT***
Level(3) Service Affecting Maintenance - GCR#180226 - Scheduled

________________________________________

Clarify Case#: 2365443
GCR #:  CHG000000180226
Primary Dates: 13 Feb 2008 01:00:00 - 13 Feb 2008 02:00:00 Eastern
Primary Dates GMT:  13 Feb 2008 06:00:00 - 13 Feb 2008 07:00:00
Location of Maintenance: Miami FL,
Summary Description of Maintenance:  Reboot - Router - Edge Router

Customer Impact:
Service
Expected Impact
Classification
Duration
Additional Notes
IP - Redundant
Outage
SA
Up to 30 minutes
DEMAND MAINTENANCE: Level 3 will be rebooting router due to bogus cells
incrementing.
IP - Non-Redundant
Outage
SA
Up to 30 minutes
DEMAND MAINTENANCE: Level 3 will be rebooting router due to bogus cells
incrementing.


_______________________________________________
Outages mailing list
Outages at isotf.org
http://isotf.org/mailman/listinfo/outages



regards,
/virendra




Edward A. Trdina III wrote:
> Just got notification that Level3 will be doing maintenance early AM EST to reboot an edge router in Miami, FL.
> 
> The ticket # for this is 2365443
> -----Original Message-----
> From: owner-nanog at merit.edu [mailto:owner-nanog at merit.edu] On Behalf Of Chris Ranch
> Sent: Tuesday, February 12, 2008 1:32 PM
> To: 'David Hubbard'; nanog at merit.edu
> Subject: RE: Level 3, again
> 
> 
> This affected us too, same impact.  No official word from Level3, but it
> looks to be back up now.  
> 
> My normal path was SJO-LAX-DAL-MIA, now it's SJO-LAX-DEN-DAL-MIA.  I can
> only speculate that it was related to the LAX-DAL link.  It lasted about an
> hour.
> 
> Chris 
> 
>> -----Original Message-----
>> From: owner-nanog at merit.edu [mailto:owner-nanog at merit.edu] On 
>> Behalf Of David Hubbard
>> Sent: Tuesday, February 12, 2008 10:06 AM
>> To: nanog at merit.edu
>> Subject: Level 3, again
>>
>>
>> Anyone know what's going on on their network?  We opened a
>> ticket but haven't heard back, sounds like they may have
>> some kind of nationwide issue going on that started in
>> Atlanta.  We've had customers on Time Warner, SBC Global,
>> AT&T and Pac Bell unable to reach us.
>>
>> David
>>
> 
> 
-----BEGIN PGP SIGNATURE-----
Version: GnuPG v1.4.2.2 (GNU/Linux)
Comment: Using GnuPG with Mozilla - http://enigmail.mozdev.org

iD8DBQFHshf5pbZvCIJx1bcRAhF4AJ0cIGH8yMgD6o51pdnFMqA8FWja+wCeLDvq
Eyf/Zce2zgnO08GpYGQ78+8=
=ak1G
-----END PGP SIGNATURE-----



More information about the NANOG mailing list