Colocation in the US.
JC Dill
lists05 at equinephotoart.com
Tue Jan 23 22:11:48 UTC 2007
Robert Sherrard wrote:
>
> Who's getting more than 10kW per cabinet and metered power from their
> colo provider?
I had a data center tour on Sunday where they said that the way they
provide space is by power requirements. You state your power
requirements, they give you enough rack/cabinet space to *properly*
house gear that consumers that much power. If your gear is particularly
compact then you will end up with more space than strictly necessary.
It's a good way of looking at the problem, since the flipside of power
consumption is the cooling problem. Too many servers packed in a small
space (rack or cabinet) becomes a big cooling problem.
jc