N+? redundancy
Michael.Dillon at radianz.com
Michael.Dillon at radianz.com
Fri Apr 15 13:31:19 UTC 2005
> And I agree re: the building entrance issue and later choke points.
> Anyone recall the time several years ago that most of the Valley was
> isolated? One route was across the ?Bay? Bridge; it was down for
> planned maintenance when backhoe fade struck around San Jose.
> How many paths is enough?
In my opinion, the following rule of thumb is reasonable.
1 path is enough for a site/enterprise that shuts
down its services evenings and weekends.
2 paths is enough for a site/enterprise that provides
a 24 hour, 7 day per week service.
3 paths is enough for a population center with under
a million inhabitants.
5 paths is enough for a population center with over
a million inhabitants.
And a very few population centers such as New York,
London, Tokyo, and Cheyenne Mountain should probably
have more than 5 paths.
--Michael Dillon