Hal Murray sez:
>
>
>
> Why is the contractor waiting around?
>
<>
> I thought the standard practice was to mark the limits of the area
> you want to dig in with "USA" (Underground Service Alert) and then
> call the USA 800 number a few days before you want to dig there.
> That gives the USA people time to contact all the utilities so they
> can come out and mark the area.
[catching up]
Often the existing service will demand their guy be on-site to
observe the digging. This is usually being done by hand, and
maybe even trowels, not shovels.
--
A host is a host from coast to coast.................wb8foz at nrk.com
& no one will talk to a host that's close........[v].(301) 56-LINUX
Unless the host (that isn't close).........................pob 1433
is busy, hung or dead....................................20915-1433