Airplane crashing into Atlanta-NAP
Nathan Stratton
nathan at netrail.net
Sun Oct 27 02:28:08 UTC 1996
On Sat, 26 Oct 1996, Ken Lam wrote:
> At 07:36 PM 10/26/96 -0400, Avi Freedman wrote:
>
> >Of course, I was half-joking, but why only one Gigaswitch? Why not two,
> >for redundancy, as is implemented at Pennsauken?
> >
> >With a backup FDDI ring?
> >And I assume, spare power supplies and processors?
>
> I assume that there are adequate rat traps and rodent bait supplies :)
Hehehe, na we just decided to build things right. We have sealed transfer
switches, and manual wraparound is it gets toasted. We also have two
separate power feeds into our 5th floor space.
P.S. We also to keep spread of fire down extended the walls to the top of
the walls so that they would act as a fire wall (i.e. fire not spread above
the drop ceiling). This also keeps people from breaking into the space
form say above the drop ceiling.
Nathan Stratton CEO, NetRail, Inc. Tracking the future today!
---------------------------------------------------------------------------
Phone (703)524-4800 NetRail, Inc.
Fax (703)534-5033 2007 N. 15 St. Suite 5
Email sales at netrail.net Arlington, Va. 22201
WWW http://www.netrail.net/ Access: (703) 524-4802 guest
---------------------------------------------------------------------------
"Therefore do not worry about tomorrow, for tomorrow will worry about
itself. Each day has enough trouble of its own." Matthew 6:34