10/7/94 SF NAP Status
Frank Liu
fcliu at srv.PacBell.COM
Sat Oct 8 00:55:59 UTC 1994
Pacific Bell San Francisco NAP status as of 10/7/94:
MCInet: Both router and DSU/CSU are connected to the NAP ATM switch
and the router is able to communication with itself through a
loopback provided by the switch.
ANS/NSFNET: The DS3 circuit is completed on 10/7/94. The router and DSU/CSU
will be connected to the NAP ATM switch on Monday, 10/10/94.
vBNS: The DS3 circuit turn-up due date is 11/1/94
SprintLink: DS3 ATM port has been reserved and the order is being work on.
RS: A DS3 ATM port was reserved and the DS3 circuit between the switch and
the RS site (Pacific Bell's NOC) was verified.
Order has been placed.
The space and 2 cabinets for housing the RS, protected power and 3
data-grade dial-up lines were ordered.
Frank