Phase 5 Step 6 Schedule
Ittai Hershman
ittai at ans.net
Tue Dec 14 20:11:17 UTC 1993
In the final step of the Phase 5 deployment, we will be upgrading both
the Washington DC CNSS and connected sites and the Hartford CNSS and
its connected sites.
Since a number of providers (PSI, Alternet, and NEARnet) have dual
attachment connectivity via these two CNSSs, we have staggered the
upgrades to minimize loss of NSFNET Backbone Service connectivity.
The following is our detailed schedule for Phase 5 Step 6:
11:00pm 12/17 CE on site at Hartford/Washington POPs
12:00am 12/18 C51, C59 Upgrade
01:00am 12/18 CE on site C40(revisit)
E133
E134
01:30am 12/18 C48, C40, E133, E134 Upgrade
03:00am 12/18 CE on site E146
03:30am 12/18 C49, C57, E146 Upgrade
05:00am 12/18 CE on site C32(revisit)
05:30am 12/18 C56, C32 Upgrade
07:00am 12/18 CE on site C72(revisit)
E145
E136
07:30am 12/18 C58, C72, E145, E136 Upgrade
Please note that the Step 6 window is scheduled from Midnight to 11:30am
on Saturday, December 18th.
-Ittai