MAE-East still no generator
Perry E. Metzger
perry at piermont.com
Sun Sep 8 16:19:46 UTC 1996
Paul A Vixie writes:
> > In other words, its silly for them not to have UPSed AC available.
>
> i agree with this but it can't be exclusive. that's why dec's palo alto
> facility has both AC and DC, each of which is UPSed and generatored.
Both is fine. Lots of telco equipment likes DC. However, having
insufficient quantities of AC to meet the demand is what I think is
silly. Installing UPSes isn't hard.
Perry